Assessing criticality levels in the data center


Jerry Burkhardt and Richard W. Dennis, Contributors
09.27.2006
Rating: -4.00- (out of 5)


IT infrastructure news
Digg This!    StumbleUpon Toolbar StumbleUpon    Bookmark with Delicious Del.icio.us    Add to Google


Negative implications of unplanned downtime are certainly chief concerns for every business. But often overlooked is the fact that no two downtime incidents are the same. One data center's momentary inconvenience could be another's demise.

For this reason, it is crucial to classify the criticality of each facility, which requires an understanding that the vulnerability of an organization is directly attributed to the weakest link in its chain. A wide range of relevant factors including HVAC and electrical systems, facility security, IT infrastructure maintenance and operations and disaster preparedness must be incorporated to ensure the reliability of the facility and its data center.

Assessing the availability and reliability of a business's critical facility using the aptly named Criticality Levels concept is useful for existing facilities and during the design process. This helps to select the proper components that complement the critical mission of the facility and safeguard its data center against downtime.

Below is an example of how these criticality levels can be determined:

  • C1 – Facilities supporting routine local office processes that are not backed up regularly. The loss of function could result in diminished productivity. However, the facility can achieve simple and rapid recovery from unplanned downtime.
  • C2– Facilities supporting critical business processes that are both local and remote. The loss of availability for a C2 facility could widely affect productivity. Full recovery after momentary unplanned downtime can potentially take hours. Maintenance downtime can be regularly scheduled.
  • C3– Back-up corporate facilities supporting and/or including critical business processes. The loss of availability widely affects productivity and directly affects customers. Full recovery after momentarily unplanned downtime can take hours or even days. Maintenance during low-risk windows

    BROWSE BY TAG
    Data Center Management Advisory Newsletter,   Data center disaster recovery planning,   Data center operations management,   Data center design and infrastructure,   Data center room design and location,   Data center disaster recovery,   Chapter 1: Disaster recovery planning,   DR planning,   VIEW ALL TAGS

    Digg This!    StumbleUpon Toolbar StumbleUpon    Bookmark with Delicious Del.icio.us    Add to Google


    RELATED CONTENT
    Data Center Management Advisory Newsletter
    Where and how to build your next data center in a down economy
    Avoid data center relocation failure: Top five pitfalls
    Understanding green IT and data center energy-efficiency regulations
    Preventing a data center power crisis
    Using chargeback to reduce data center power consumption: Five steps
    Using Linux in a data center consolidation management strategy
    Packaged chiller plants increase data center cooling efficiency
    Chiller optimization for data center infrastructure
    How many data centers are sufficient for disaster recovery? Two, three, or more?
    Data growth: The worst enemy of your recovery time objective

    Data center disaster recovery planning
    Lower disaster recovery costs with open source replication tools
    Apple updates Xserve, Symantec ships DR monitoring software: News in brief
    Data center disaster recovery planning
    Google opts for battery backup over UPS: News in brief
    Avoiding disaster recovery pitfalls in VMware and Linux: Rejecting default settings
    Make IT change management part of your disaster recovery plan
    Using carrier colocation in your data center disaster recovery plan
    Gmail outage caused by data center rolling blackout
    SunGard opens new data center, and other facility news in brief
    Disaster recovery planning tools: Are they worth it?
    Data center disaster recovery planning Research

    Data center room design and location
    Hot-aisle vs. cold-aisle containment: Liebert and APC face off
    Core4 sells more efficient -- and costly -- CRACs
    Hewlett-Packard demonstrates its Performance Optimized Data center (POD)
    Schneider: IT and energy management control systems bring efficiency
    Sun Microsystems releases new version of OpenSolaris
    Where and how to build your next data center in a down economy
    HP updates mission-critical services: News in brief
    Ascent builds customizable data center hosting facility: News in brief
    Data center air recycling saves cash-strapped greenhouse
    At colo data center, air mixing happens up high
    Data center room design and location Research

    RELATED GLOSSARY TERMS
    Terms from Whatis.com − the technology online dictionary
    Business Continuity and Disaster Recovery (BCDR)  (SearchStorage.com)
    high availability  (SearchDataCenter.com)
    RAIN  (SearchDataCenter.com)
    uninterruptible power supply  (SearchDataCenter.com)
    Uptime Institute, Inc.  (SearchDataCenter.com)

    RELATED RESOURCES
    2020software.com, trial software downloads for accounting software, ERP software, CRM software and business software systems
    Search Bitpipe.com for the latest white papers and business webcasts
    Whatis.com, the online computer dictionary


    can be scheduled monthly or quarterly.

  • C4– Primary corporate facilities that support and/or include critical business processes. The loss of availability widely affects productivity and directly affects customers. Full recovery after momentarily unplanned downtime can take hours or even days. Online maintenance with moderate risk windows can be scheduled monthly or quarterly with blackout periods, and maintenance shutdown is extremely difficult to schedule.
  • C5– Primary corporate facilities supporting and/or including core business processes. The loss of availability directly translates to the facility's bottom line. Full recovery after momentary unplanned downtime can take days to possibly weeks. Online maintenance with low-risk windows can be scheduled quarterly or annually with blackout periods. Maintenance shutdown cannot be scheduled.
  • C6– Large corporate data centers supporting and/or including core business processes and are, typically, a network of remote data centers that work together. The loss of availability poses widespread circumstances that can affect national security and public safety. Full recovery after momentary downtime can take weeks to months and all maintenance must be performed online and must be extremely low-risk.
  • C7 and beyond– Future levels for continued growth and evolution of the critical facility.

    Enabling facility planners and IT directors to assess the importance and level of quality needed for various external components, such as standby power, security, IT configuration and IT redundancy is the primary purpose for these definitions. For example, a C6 facility such as a large corporate data center must have significantly more IT redundancy than a C1 facility that is simply supporting office processes.

    When facility designers understand the level of criticality, combined with an assessment of all of the external components supporting its operations, they are enabled to provide the needed flexibility, redundancy and security to support the organization's critical mission.

    About the authors:

    Jerry Burkhardt is the P.E. and vice president of commissioning services at Syska Hennessy Group. He has over 21 years of specialized experience in critical and live environments.

    Richard Dennis is the P.E. and vice president of national commissioning services for Syska Hennessy Group. He has over 30 years of professional engineering experience in design management, construction, and facility operations.

    Rate this Tip
    To rate tips, you must be a member of SearchDataCenter.com.
    Register now to start rating these tips. Log in if you are already a member.


    Submit a Tip




    DISCLAIMER: Our Tips Exchange is a forum for you to share technical advice and expertise with your peers and to learn from other enterprise IT professionals. TechTarget provides the infrastructure to facilitate this sharing of information. However, we cannot guarantee the accuracy or validity of the material submitted. You agree that your use of the Ask The Expert services and your reliance on any questions, answers, information or other materials received through this Web site is at your own risk.



  • White Papers - Data Center Networking

    The Intel IT Technology Center - Power, Performance and Mobility Solutions

    HomeNewsTopicsITKnowledge ExchangeTipsBlogsMultimediaWhite PapersEvents
    About Us  |  Contact Us  |  For Advertisers  |  For Business Partners  |  Site Index  |  RSS
    SEARCH 
    TechTarget provides technology professionals with the information they need to perform their jobs - from developing strategy, to making cost-effective purchase decisions and managing their organizations' technology projects - with its network of technology-specific websites, events and online magazines.

    TechTarget Corporate Web Site  |  Media Kits  |  Site Map




    All Rights Reserved, Copyright 2005 - 2009, TechTarget | Read our Privacy Policy
      TechTarget - The IT Media ROI Experts