Experian drills backup water supply to cool data center

By Mark Fontecchio, News Writer
24 Nov 2008 | SearchDataCenter.com

IT infrastructure news
Digg This!    StumbleUpon Toolbar StumbleUpon    Bookmark with Delicious Del.icio.us    Add to Google

Three summers ago, a 76-inch main line that feeds water from Lake Lavon to 29 cities and towns in Texas broke. That was a disaster for credit services giant Experian, which relied on city water to supply the chillers that cool its McKinney data center.

For more on data center cooling:
Green UPS Tier IV data center water-side economizers

Servers don't sweat: Raise your chilled-water temp

Data center cooling nightmares

"We lost all city utility as far as water pressure," said Russ Burlew, the data center facility manager. "It took three and a half days to repair that line, and we were without water. We had vendors come in with water trucks and pumps to keep our tower full."

"When everyone talks about Tier IV [data center], they talk about power and cooling redundancy," Burlew continued. "But they don't think a lot about water. But in our case, without water, you don't have cooling." After the water main line broke, Burlew began looking for a backup water supply. And eventually he and his data center staff took a page from the book of the old Texas oil men: You drill for it.

Digging a hole to get out of one
That's right; Experian dug a well. It hired a contractor to drill 1,200 feet into the ground to hit the Woodbine Aquifer, which runs through 17 counties in north central Texas. Burlew said that in the case of another emergency like the breaking of the water main line, the McKinney data center -- which is a production data center for the company -- can switch to well water indefinitely and automatically.

In our case, without water, you don't have cooling.
Russ Burlew
data center facility manager, Experian

Drilling a well was costly, at a price tag of about $150,000, according to Burlew. But that pales in comparison to the cost of its data center not being up and running.

"If we lost cooling and operations stopped, we would make up that money in seconds," he said.

To avoid downtime, Burlew and his team have automated the process of switching from city water to the well using controls at the chilled-water plant. Experian has also taken precautions to ensure a graceful cutover by first shutting down the valve to the city water so that, as Burlew put it, "we won't back-feed well water into city water."

Permits, valve controls, capacity and filtering
The absence of regulations meant that Experian didn't have to submit a permit to drill the well. "It's an open range to drill as you see fit," Burlew said. Not every part of the country has that luxury, and even that area of Texas might not in the near future. Burlew said the 17 counties served by the Woodbine Aquifer are in negotiations to form a consortium that would regulate access to the aquifer. Luckily, the Experian well has already been dug and, should regulatory changes be made, will be grandfathered in.

But there was concern about whether the well could supply enough water to the facility: 30 gallons of water per minute, according to Burlew. Luckily, Experian just made it; once it drilled the well, it determined that the well could supply 32 gallons of water per minute.

There was also concern about the cleanliness of the well water, and whether it would need extensive filtering.

"There is a fine silt at the bottom of the aquifer that you'll see at initial startup," Burlew said. "That's what we're concerned with. If that goes through the chiller veins, it could scratch up the tubing, causing lost performance at the chillers and be costly."

The drilling company said the silt is common in well water, and that it would clear up after a few months of pumping. Nevertheless, Experian sends water samples to a lab to assess water quality and how it might affect the chillers. Since the mechanics of the well were completed only a couple months ago, it's still early in the process, and Experian will have a chance to install a filtering system if they need it.

The unknowns of well drilling and other backup-water options
Robert McFarlane, a data center design expert and a principal at New York-based Shen Milsom & Wilke Inc. , said that well drilling is an uncommon way to get backup water for a data center, because there are so many question marks.

"The problem with well water is that, until you reach it, you don't know what condition it's in, and what kind of minerals are in it," he said. "If it's more like spring water, then it can be great."

In addition, unless you have assurances that there is a water supply somewhere underground, it could be like digging to China: You'll never get there.

"The thing about wells is you can drill, but it doesn't mean you're going to hit something you want," he said. "How many holes do you have to sink before you know you're going to hit what you need?"

Experian's, however, it knew it could tap into the resources of the Woodbine Aquifer.

McFarlane said a more common approach to backup water is to dig a retention pond, which Experian also considered. For those data centers that have the highest demands for availability, those retention ponds usually are large enough to supply water to chiller plants for a week or so. At that point, the company will need to decide whether they'll be able to bring that primary site back on or transfer to a backup location.

"It's all part of the whole disaster recovery plan, and every organization treats it differently," McFarlane said. "The decision is based on how long you think you're going to have to run and how long you think it will take to solve the problem."

Let us know what you think about the story; email Mark Fontecchio, News Writer. You can also check out our Data Center Facilities Pro blog.



Tags: Data center coolingData center disaster recovery planningData center room design and locationVIEW ALL TAGS

Digg This!    StumbleUpon Toolbar StumbleUpon    Bookmark with Delicious Del.icio.us    Add to Google



RELATED CONTENT
Data center cooling
IT wish list: Better ways to analyze data center environmental metrics
End users still cool on Iceland as a data center site
Air-side economizers reduce energy use at NetApp data center
Sizing computer room air conditioners for data center energy efficiency
Should you comply with Article 645 of the National Electrical Code?
How to identify and remediate data center hot spots
Data center humidity levels source of debate
Air-side and water-side economizers in the data center
Amazon data center facility engineer touts radical cooling tactics
Colo taps cold weather, river for green data center
Data center cooling Research

Data center disaster recovery planning
Data center pros must prepare for increased space weather
Are you wasting disaster recovery budget to avoid employee inconvenience?
Four ways to extend data center UPS battery life
Why SunGard uses flywheel UPSes in its data centers
Lower disaster recovery costs with open source replication tools
Apple updates Xserve, Symantec ships DR monitoring software: News in brief
Data center disaster recovery planning
Google opts for battery backup over UPS: News in brief
Avoiding disaster recovery pitfalls in VMware and Linux: Rejecting default settings
Make IT change management part of your disaster recovery plan
Data center disaster recovery planning Research

Data center room design and location
Air-side economizers reduce energy use at NetApp data center
Data center location selection: Incentives can tip scales
Notes from AFCOM Data Center World: Day one
Microsoft cuts ribbon on mega data center
Hot-aisle/cold-aisle containment takes hold
How to identify and remediate data center hot spots
Colo taps cold weather, river for green data center
Preventing particle and gas contamination in the data center
Cleaning under the raised-floor plenum: Data center maintenance basics
AMD augments six-core Opteron chip line: News in brief
Data center room design and location Research

RELATED GLOSSARY TERMS
Terms from Whatis.com − the technology online dictionary
ambient temperature  (SearchDataCenter.com)
ASHRAE  (SearchDataCenter.com)
Calibrated Vectored Cooling  (SearchDataCenter.com)
compaction  (SearchDataCenter.com)
computer room air conditioning unit  (SearchDataCenter.com)
data center chiller  (SearchDataCenter.com)
green data center  (SearchDataCenter.com)
hot/cold aisle  (SearchDataCenter.com)
HVAC  (SearchDataCenter.com)
water cooling  (SearchDataCenter.com)

RELATED RESOURCES
2020software.com, trial software downloads for accounting software, ERP software, CRM software and business software systems
Search Bitpipe.com for the latest white papers and business webcasts
Whatis.com, the online computer dictionary



Efficient Management for Data Centers
HomeNewsTopicsITKnowledge ExchangeTipsBlogsMultimediaWhite PapersEvents
About Us  |  Contact Us  |  For Advertisers  |  For Business Partners  |  Site Index  |  RSS
SEARCH 
TechTarget provides technology professionals with the information they need to perform their jobs - from developing strategy, to making cost-effective purchase decisions and managing their organizations' technology projects - with its network of technology-specific websites, events and online magazines.

TechTarget Corporate Web Site  |  Media Kits  |  Site Map




All Rights Reserved, Copyright 2005 - 2009, TechTarget | Read our Privacy Policy
  TechTarget - The IT Media ROI Experts