Many data centers strive to be fully "lights out," but is that such a wise idea? Last week, that was the question raised by Mike Hagan, the senior vice president of operations at Lee Technologies, at an AFCOM Data Center World session in Orlando, Fla.

For more on lights-out data centers:
Data center managers primed for IT process automation

Microsoft data center trailers are tornado bait

Chicago colocation facility robbed -- again

A lights-out data center means getting as many people out of the data center as possible to reduce staffing costs and eliminate the possibility of human error. But according to Hagan, at least on the facility and infrastructure side, it can be dangerous to pull out the troops.

Indeed, said Hagan, there are risks. "You have to get into the question of evaluation," he said. "It's not what taking the cost of the individual out would be. It's the cost of what not having him there is."

Hagan does have a pawn in the game; one of the major services provided by Lee Technologies is data center staffing. Still, Hagan's session –"Lights-Out Data Center: Don't Believe It" – was packed, and during the Q&A session, some members in the audience voiced concerns similar to Hagan's. (Of course, some of those naysayers may be data center facility staffers who fear being replaced by automation software.)

The biggest stumbling block we see is inconsistency in procedure.
Mike Hangan,
senior VP of operations, Lee Technologies

Hagan's colleague Don Denning, a facility operations manager for Lee Technologies, said that sometimes there is no replacement for a warm body.

Case in point, at one brand-new site that Denning helps manage, the building management system indicated that an air handler had shut off, so data center staff went to look at it and found that the air handler ran fine but the building management system was wrong. Had no one been on-site to identify the problem, the company might have overcompensated by running other air handlers harder or starting up a backup air handler, thereby wasting energy and taxing power capacity, he said.

Yahoo: Among the lights-out skeptics
Even among mammoth data center operators, there is some debate about lights-out data centers. While huge companies like Google have moved toward a lights-out data center as much as possible, Yahoo has taken a different course.

"We are believers that there is a significant risk reduction by having people in the data center," said Kevin Timmons, the company's vice president of operations. While Yahoo tries to minimize the number of people on the data center floor among server and IT equipment racks, "we've seen the benefits of having people in the data center 24 hours a day," he said.

Nevertheless, the imperative to reduce staff and go lights-out remains, and data center managers should prepare themselves for the eventuality. To that end, Lee Technologies' Hagan recommended cross-training IT and facility personnel. If an edict comes down to cut staff, a data center won't lose as much institutional knowledge as it would otherwise.

"If you have eight facility guys, and 12 IT guys, you may want to cross-train in case you have to eventually go down to 15 total," he said.

Hagan also recommended standardizing what a lights-out data center means throughout an organization. For businesses with multiple data centers, lights-out may mean something different in each location, and getting the different facilities to work together as single operations team can be a challenge. It can become especially problematic if staff from one facility is consolidated or moved to a different site.

"The biggest stumbling block we see is inconsistency in procedure," Hagan said.

Let us know what you think about the story; email Mark Fontecchio, News Writer. You can also check out our Data Center Facilities Pro blog.



Tags: Data center jobs and staffing and professional developmentData center disaster recoveryData center design and constructionVIEW ALL TAGS

Digg This!    StumbleUpon Toolbar StumbleUpon    Bookmark with Delicious Del.icio.us    Add to Google



RELATED CONTENT
Data center jobs and staffing and professional development
How to find a job in the data center: IT job hunt tips
OSU's Open Source Lab offers students systems management experience
'Grace Hopper and the Invention of the Information Age': Book review
Iron Man 2 tops the list of geek flick picks for 2010
Gadget geeks look back at the greatest gizmos of 2009
The top data center 2010 trends
Message to data center managers: Speak up!
Bring in facilities and finance groups for data center projects
Key aspects of designing a data center for maintainability
HP user group Connect president reflects on group gains

Data center disaster recovery
Data center flywheel gets thumbs-up from colo provider
Data center pros must prepare for increased space weather
How will ultra-low sulfur diesel affect data center generator performance?
Are you wasting disaster recovery budget to avoid employee inconvenience?
Uptime Institute opens data center availability tiers
Four ways to extend data center UPS battery life
Why SunGard uses flywheel UPSes in its data centers
Lower disaster recovery costs with open source replication tools
Apple updates Xserve, Symantec ships DR monitoring software: News in brief
Data center disaster recovery planning
Data center disaster recovery Research

Data center design and construction
Hewlett-Packard pushes smaller containerized data center
Facebook bets on coal for new Oregon data center
Oracle energy czar brings data center containment into vogue
Hot-aisle/cold-aisle containment slideshow
eBay's hot/cold-aisle containment in the data center
Yahoo's data center cold aisle containment
eBay uses plastic sheeting for data center hot cold aisle containment
Liebert's data center cold aisle containment product
Hot aisle / cold aisle containment in pictures
APC's data center hot-aisle containment

RELATED GLOSSARY TERMS
Terms from Whatis.com − the technology online dictionary
high availability  (SearchDataCenter.com)
RAIN  (SearchDataCenter.com)
uninterruptible power supply  (SearchDataCenter.com)
Uptime Institute, Inc.  (SearchDataCenter.com)

RELATED RESOURCES
2020software.com, trial software downloads for accounting software, ERP software, CRM software and business software systems
Search Bitpipe.com for the latest white papers and business webcasts
Whatis.com, the online computer dictionary



Efficient Management for Data Centers
HomeNewsTopicsITKnowledge ExchangeTipsBlogsMultimediaWhite PapersEvents
About Us  |  Contact Us  |  For Advertisers  |  For Business Partners  |  Site Index  |  RSS
SEARCH 
TechTarget provides technology professionals with the information they need to perform their jobs - from developing strategy, to making cost-effective purchase decisions and managing their organizations' technology projects - with its network of technology-specific websites, events and online magazines.

TechTarget Corporate Web Site  |  Media Kits  |  Site Map




All Rights Reserved, Copyright 2005 - 2010, TechTarget | Read our Privacy Policy
  TechTarget - The IT Media ROI Experts