kantver - Fotolia

Evaluate Weigh the pros and cons of technologies, products and projects you are considering.

How do I figure size requirements for a new UPS unit?

Your data center UPS needs are dependent on a variety of factors. Develop configurations and determine the estimated UPS capacity that will meet your current and future needs.

So you need an uninterruptible power supply unit, but you're having trouble sizing it. How do you figure it out? 

Some uninterruptible power supply  (UPS) systems are rated in kilowatts (kW) and others in kilo-volt-amperes (kVA).

UPS terminology and facts

KW and kVA simply mean 1,000 watts or 1,000 volt-amperes -- the kilo prefix being used for larger numbers.

The basic rule of physics that watts = volts x amps is based on direct current circuits. Alternating current (AC) supplies our buildings and equipment. AC is more efficient for power companies to deliver, but when it hits the equipment's transformers, it exhibits a characteristic known as reactance.

Reactance reduces the useful power (watts) available from the apparent power (volt-amperes). The ratio of these two numbers is called the power factor (PF). Therefore, the actual power formula for AC circuits is watts = volts x amps x power factor. Unfortunately, the PF is rarely stated for most equipment, but it is always a number of 1.0 or less, and about the only thing with a 1.0 PF is a light bulb.

For years, large UPS systems were designed based on a PF of 0.8, which meant that a 100 kVA UPS would only support 80 kW of real power load.

The majority of large, commercial UPS systems are now designed with a PF of 0.9. This recognizes that most of today's computing technology presents a PF of between 0.95 and 0.98 to the UPS. Some UPS systems are even designed with PFs of 1.0, which means the kVA and kW ratings are identical (100 kVA = 100 kW). However, since the IT load never presents a 1.0 PF, for these UPS systems, the actual load limit will be the kVA rating.

Regardless of how the ratings are stated, a 100 kVA UPS will never support an actual 100 kW load in the real world of the data center. The only way to really know how near you are to capacity is to read the UPS display. The Percent Load will tell you how close you are to the maximum in either kW or kVA, but be aware that this percentage will be displayed for the most heavily loaded phase, not for the total UPS capacity. 

Large UPS systems are three-phase. In the U.S., you get 120 volts between any one of the phases and what's called the neutral conductor, and you get 208 volts -- not 220 or 240 -- between any two phase conductors. In Europe, you get 230 or 240 volts between any phase and neutral. Connections aren't made between phases. Unless the loads on all three phases are close to equal, you won't be as close to maximum total capacity as the display says you are. You need to further check the loads on all three phases to determine that. Take, for example, a 100 kVA UPS with a 0.9 PF, or 90 kW capacity. If Phase A is loaded to 95%, and Phase B to 60%, and Phase C to only 25%, the UPS will still have 40 kVA or 36 kW unused. That's 40% of its capacity remaining, despite the 95% reading.

Neither the kW nor the kVA capacity of the UPS can be exceeded, but because of the higher PF numbers, it is usually the kW rating that governs today. There are, however, some UPS systems on the market that are PF-corrected so that the kW and kVA ratings are the same.

Phase imbalance calculations
An example of phase imbalance calculations.

Nameplate data on UPS systems

The biggest problem when figuring size requirements for UPS units is determining their actual load. Many data hardware manufacturers still provide inadequate or misleading power data on their equipment. Bigger manufacturers are usually linked to or have a configurator on their websites. These tend to give quite accurate information if used correctly. But no tool can give you an accurate estimation of total load. It's up to you to develop realistic numbers.

Beware of using the nameplate. This is a legality rating, and will usually give a much higher volt-ampere rating than the unit will ever draw. For example, consider a unit with a nameplate that reads 90 - 240 volts at 4 - 8 amps with a 500 watt (W) power supply.

First, the numbers are backward. The larger amperage goes with the lower voltage. If you assume a nominal 120 volts at 8 amps, you get 960 VA. A PF of 0.95 would yield 912 watts. No power supply is that inefficient, and a power supply almost never runs at full power. Therefore, it is highly unlikely that this device will ever draw more than 500 watts of power, but if you want to be really conservative, multiply by 1.1 and figure 550 Ws of input power.

And don't get trapped by dual-corded equipment. The power supplies share the load and either one is supposed to be able to carry the full load. Therefore, a unit with two 500 W supplies should still be figured as if it had only one.

UPS capacity ratings

Once you have a realistic load estimate, plan to run a UPS around 80% of actual rated capacity. That provides headroom for peak operating conditions, gives you capacity to install a duplicate system before you decommission an old one, or lets you absorb a little growth before you outgrow the unit. For a planned load of 80 kW, a 1.0 PF UPS rated at 100 kVA/100 kW should be sufficient if you keep your loads phase-balanced within about 5%. A UPS with a 0.9 PF will need a higher kVA rating; 125 kVA would give you 112.5 kW capacity, which also gives you a little additional headroom.

If you foresee substantial near-term growth, consider a modular UPS. These come in two flavors: a frame sized for more than you need, but with physical UPS and battery modules installed only as required; or a system of higher total capacity, but with firmware-configured to limit it to a lesser load until you need more. Either way, you only pay for what you need now, and buy the additional capacity as it's required. The savings is not just capital cost. A UPS also runs more efficiently when it's loaded to higher capacity, so you save in electrical operating costs as well. Of course, with a 2N redundant UPS, you'll actually run each UPS at half the total load, which makes it even more important to size correctly. It can be very inefficient to run below 40%.

The last consideration is generator loading. Different UPS designs present different electrical characteristics to a generator. Your electrical engineer or facilities electrician will need to examine both the UPS and generator characteristics to make sure the generator won't stall when the UPS load is suddenly switched to it in an emergency.

Next Steps

Balance three-phase power

Add fuel cell generators

To LBS or not to LBS

More on UPS sizing

Maximizing UPS performance when sizing goes wrong

This was last published in February 2017

Dig Deeper on Data center design and facilities

PRO+

Content

Find more PRO+ content and other member only offers, here.

Join the conversation

3 comments

Send me notifications when other members comment.

By submitting you agree to receive email from TechTarget and its partners. If you reside outside of the United States, you consent to having your personal data transferred to and processed in the United States. Privacy

Please create a username to comment.

How did you figure out the right size requirements for your UPS system?
Cancel
how to get the maximum required UPS system from my following loads
1. 1500 kva CCTV cabinet
2. 2000 kva Telecom Cabinet
3. Switches and RTU's 2500 kva
best regards
Cancel
Total load of Data center is 200kW. How can I design UPS system with n+1 redundancy.
Cancel

-ADS BY GOOGLE

SearchWindowsServer

SearchEnterpriseLinux

SearchServerVirtualization

SearchCloudComputing

Close