QUESTION POSED ON: 29 June 2006
We want your help for the following question about NFPA 75:

Our company is designing a clean agent fire protection system for a data center. There are two rooms with false floor each, so the customer wants the system have four independent suppression zones in order to reduce the quantity of agent in a eventual discharge. It means one suppression system for each false floor and each computer room.

  • Besides the tightness between false floor and computer room, what kind of considerations we must take?
  • Are there some disadvantages or contradicting any standard?


  • BROWSE BY TAG
    Data center design and infrastructure,   Data center fire suppression,   VIEW ALL TAGS

    Digg This!    StumbleUpon Toolbar StumbleUpon    Bookmark with Delicious Del.icio.us   



    RELATED CONTENT
    Data center fire suppression
    Drawbacks to hot/cold aisle containment
    Hot-aisle/cold-aisle containment stokes fire-code issues
    The Planet data center hosting company suffers major electrical fire
    The data center EPO button: Is it even necessary?
    Dry pre-action fire suppression systems
    Halon and FM-200, part two
    Selecting a sprinkler system: Dependent on local building code regulations?
    Gas fire suppression systems
    Water versus gas-based data center fire suppression
    Seven steps to data center fire planning

    RELATED GLOSSARY TERMS
    Terms from Whatis.com − the technology online dictionary
    limited combustible cable  (SearchDataCenter.com)

    RELATED RESOURCES
    2020software.com, trial software downloads for accounting software, ERP software, CRM software and business software systems
    Search Bitpipe.com for the latest white papers and business webcasts
    Whatis.com, the online computer dictionary


    Utilizing separate suppression 'zones' for both above floor and sub-floor spaces is a common practice in areas where the subfloor contains a significant hazard/fuel load.

    Considerations:

  • Tightness between 'zones' is certainly one, as you have mentioned. The biggest concern here is likely not to be the physical tightness of the interlocking elements of the sub-floor, but rather the likelyhood of designed ventilation (floor tiles with perforations or tiles left open under cabinets) used as part of the AC strategy. Make sure your fire suppression strategy synchronizes adequately with your AC strategy in this regard.
  • Generally speaking, use the same suppression agent for these two hazards. Although there is unlikely to be any major performance or health based issues with using different agents -- the NFPA 2001 standard does provide guidance in this area, section 1.8
  • Ensure that both zones of protection are adequately covered by independent fire and/or smoke detection means. This should also take into consideration the accessibility of these devices, particularly in the subfloor space. Service/maintenance of subfloor smoke detectors can frequently be problematic and is therefore sometimes (wrongly) neglected alltogether.
  • Ensure design and installation of the suppression system piping meets the equipment manufacturers specifications, particularly in the sub-floor space. This space can frequently be crowded with wiring and a challenge to install the piping correctly. Note things like nozzle types (sidewall or 360 degree), nozzle orientations (facing up or facing down) and t-split orientations to ensure they comply with the manufacturers specifications.

    Although a good local contractor will design and install correctly, there are many ways to cut corners in this challenging type of installation. Take the responsibility to double and triple check installation practices and design elements to ensure they meet with the manufacturers specifications.




  • Search and Browse the Expert Answer Center
    Search and browse more than 25,000 question and answer pairs from more than 250 TechTarget industry experts.
    Browse our Expert Advice



    Building Green Data Centers
    HomeNewsTopicsITKnowledge ExchangeTipsBlogsMultimediaWhite PapersEvents
    About Us  |  Contact Us  |  For Advertisers  |  For Business Partners  |  Site Index  |  RSS
    SEARCH 
    TechTarget provides technology professionals with the information they need to perform their jobs - from developing strategy, to making cost-effective purchase decisions and managing their organizations' technology projects - with its network of technology-specific websites, events and online magazines.

    TechTarget Corporate Web Site  |  Media Kits  |  Site Map




    All Rights Reserved, Copyright 2005 - 2009, TechTarget | Read our Privacy Policy
      TechTarget - The IT Media ROI Experts